Foundation Isolation System with FAEBI, Level Control System, and Prefabricated Concrete Slabs

Foundation Isolation System with FAEBI, Level Control System, and Prefabricated Concrete Slabs

Example: Stamping Machine Type PIVATIC PCC80 TTI + HT

Machine weight including work piece is approximately 25 tons (23 metric tons).

Dynamic vertical forces approximately 13,500 lb-f (60 KN), horizontal forces approximately 6,750 lb-f (30 KN).

Foundation block: approximately 16′ 9″ x 11′ 6″ x 3′ 4″ (5.1 x 3.5 x 1 m); Weight approximately 44 US tons (40 metric tons).

BILZ® Equipment:

8 x BILZ®-FAEBI® 580 HD with mechanic level control system LCV and following services:

• Foundation design

• Static foundation calculation

• Form work plans

• Steel and bending schedule list

Special request:

Target: loss of production not longer than 3 weeks. Small space from the revision channel trough to foundation block. Very low horizontal movement of the machine was excepted. Efficiency of the isolation of more than 80 % was requested.